Mining analysis results

The Mining Analysis screen compares planned mining with actual mining for the selected period, location and configuration. Use the results to review movement variances and compliance with the mine plan.

Mining quantities and variances

  • Chart information: Identifies the mine plan, primary attribute and units displayed in the chart. Click the information icon to view additional mine plan details.
  • Movement metrics: Summarise Direct Feed, Stockpiling, Waste Movements and any unknown movements. Categories reflect the grouping options selected in the Configure panel. Each percentage shows the variance between actual and planned values for the selected primary attribute.
  • Mine Production: Summarises the overall variance between total planned mining and total actual mining, including ore and waste.
  • Planned Mining: Shows the total quantity scheduled to be mined in the selected mine plan. The table provides planned tonnes and grades for each movement category and grouping.
  • Actual Mining: Shows the total quantity recorded as mined in actual haulage data. The table provides actual tonnes and grades for each movement category and grouping.
  • Mining variance waterfall: Shows how direct feed, stockpiling, waste movements and any unknown movements contribute to the difference between Planned Mining and Actual Mining.

Mine plan compliance

Mine Plan Compliance compares planned and mined tonnes at the lowest location level in the selected mine plan. It identifies material mined according to the plan, material planned but not mined, and material mined outside the plan. In the Configure panel, select whether to calculate compliance using surveyed tonnes or truck tonnes. See Configure the mining analysis.

The compliance waterfall breaks planned and mined tonnes into these categories:

  • Planned: Total tonnes included in the selected mine plan.
  • Planned and not Mined: Planned tonnes that were not recorded as mined.
  • Planned and Mined: Tonnes both planned and recorded as mined at the corresponding plan location.
  • Mined and not Planned: Mined tonnes not included in the selected mine plan.
  • Mined: Total tonnes recorded as mined.

The categories have the following relationships:

Planned and not Mined + Planned and Mined = Planned
Planned and Mined + Mined and not Planned = Mined